Alabama Lien Waiver Guide
Alabama accepts custom lien waiver forms. No statutory forms are mandated.
Key Information
Waiver Type
Non-Statutory
Filing Deadline
6 months from last furnishing labor or materials
Notice Requirements
No preliminary notice required for original contractors. Subcontractors must provide notice within 30 days of first furnishing.
Key Statutes
Ala. Code §35-11-210 et seq.
Waiver Types in Alabama
Conditional Waiver on Progress Payment
Waives lien rights for a specific progress payment, but only upon actual receipt of payment. Protects the claimant if the check bounces or payment fails.
Unconditional Waiver on Progress Payment
Immediately and unconditionally waives lien rights for a specific progress payment amount, regardless of whether payment has actually been received.
Conditional Waiver on Final Payment
Waives all lien rights upon receipt of the final payment. The waiver is conditioned on actual receipt of the specified final payment amount.
Unconditional Waiver on Final Payment
Immediately and unconditionally waives all lien rights. This is the most comprehensive waiver and should only be signed after final payment is confirmed in your account.
Alabama Lien Waiver Rules
Alabama does not mandate statutory waiver forms. Custom lien waivers are enforceable. Waivers should clearly identify the project, amount, and parties. Partial waivers are recognized for progress payments.