Nebraska Lien Waiver Guide

Nebraska accepts custom lien waiver forms. No statutory forms are mandated.

Key Information

Waiver Type

Non-Statutory

Filing Deadline

120 days from last furnishing labor or materials

Notice Requirements

Subcontractors must provide a 10-day preliminary notice before filing a lien.

Key Statutes

Neb. Rev. Stat. §52-101 et seq.

Waiver Types in Nebraska

Conditional Waiver on Progress Payment

Waives lien rights for a specific progress payment, but only upon actual receipt of payment. Protects the claimant if the check bounces or payment fails.

Unconditional Waiver on Progress Payment

Immediately and unconditionally waives lien rights for a specific progress payment amount, regardless of whether payment has actually been received.

Conditional Waiver on Final Payment

Waives all lien rights upon receipt of the final payment. The waiver is conditioned on actual receipt of the specified final payment amount.

Unconditional Waiver on Final Payment

Immediately and unconditionally waives all lien rights. This is the most comprehensive waiver and should only be signed after final payment is confirmed in your account.

Nebraska Lien Waiver Rules

Nebraska does not mandate statutory waiver forms. Custom waivers are enforceable. Nebraska's construction lien law requires careful attention to preliminary notice requirements for subcontractors. Waivers should be clear and specific about the payment covered.